Excerpt of an interior BOQ showing three lines, a wardrobe in square feet, kitchen base units in running feet and electrical points in numbers, each with quantity, rate and amount

Most interior BOQs that cause trouble are not wrong because of bad rates. They go wrong because of format: a wardrobe priced per piece in one quote and per square foot in the next, a painting line with no mention of coats, a "miscellaneous" lump sum nobody can explain at handover, or a sheet where the studio's cost and the client's price sit in the same column.

The format that holds up is simple. Group lines into sections by room, tag each line with its trade, write one item per line with its specification, use one agreed unit per item type, and keep two rates on every line: what it costs you and what you charge. Contingency and GST go once, at the summary, not hidden inside rates. This guide walks through each part, with a worked 2 BHK BOQ whose numbers add up and a template you can download.

What an interior BOQ is, and what it is not

A bill of quantities (BOQ) lists every piece of work and supply on a project, with a quantity, a unit and a rate for each. For an interior studio it is the costing baseline: the document you price from, the one the quotation is built from, and the one procurement and site teams order and execute against. Four documents get mixed up often enough to separate them clearly.

DocumentWhat it answersWho sees itLevel of detail
Rough estimateRoughly what will this cost?Client, early in the conversationPer sq.ft or per room, no line items
BOQWhat exactly is in scope, how much of it, and at what cost and price?Your studio (internal rates); client sees a version without themEvery line itemised with unit, quantity and rates
QuotationWhat will the client pay, on what terms?ClientClient rates, GST, payment terms, validity, exclusions
Bill of materialsWhat do we need to buy?Purchase and site teamMaterials only, no labour or services

Keeping the BOQ as the internal source and deriving the quotation from it is what stops the two from drifting apart. If a client asks for a cheaper laminate, you change the BOQ line and the quotation follows, instead of editing two spreadsheets and hoping they still agree.

The columns every interior BOQ needs

Tender BOQs from banks and government offices use a short column set: description, unit, quantity, rate and amount. A studio BOQ needs a few more, because it is used for costing and margin as well as for the client.

ColumnWhat goes in itWhy it matters
SectionThe room or area: Kitchen, Master Bedroom, Whole ApartmentClients read and approve scope room by room
Item nameShort name with the key specification: "Wardrobe, 18mm BWP carcass, 1mm laminate shutters"A name without a specification invites a dispute later
CategoryThe trade: Carpentry & Woodwork, False Ceiling & POP, Paint & FinishesLets you total and assign work by trade (see below)
DescriptionInclusions and exclusions: hinges, edge-banding, number of coats, what is extraThis is where most scope arguments are settled
DimensionsThe drawn size: 8' × 7', 10 rftLets anyone check the quantity without opening the drawing
Unitsq.ft, rft, nos, set, LSOne unit per item type, used the same way on every project
QuantityThe measured quantity in that unitComes from the site survey and drawings, not from memory
Internal rateYour cost per unit: material, labour, transport, your vendor's rateThe basis for margin; never shown to the client
Client rateYour selling price per unit, before GSTWhat the client sees and approves
Amounts and marginQuantity × each rate; margin % per lineShows which lines earn and which are thin
One BOQ line for a master bedroom wardrobe broken into four parts: section and item with specification, size 8 by 7 feet measured as 56 square feet of shutter face, an internal rate of 1,200 rupees and a client rate of 1,850 rupees, giving a client amount of 1,03,600 rupees and a 35.1 percent margin
One wardrobe line from the worked example. Each column answers one question. Rates are illustrative.

If your current sheet has a single rate column, that is the first thing to change. A sheet that holds only the selling price cannot tell you, three weeks later, whether the project is still profitable after the client switched from laminate to acrylic shutters.

Sections: group by room, tag by trade

Studios argue about whether a BOQ should be organised by room or by trade. Each answers a different reader, so the practical answer is to do both: make the room the section and record the trade in the category column.

QuestionRoom-wise sectionsTrade-wise sections
Who reads it bestClients, who think in roomsYour purchase team, vendors and site supervisor
Good forApprovals, cutting scope room by room, matching drawingsOrdering, assigning carpenters and painters, comparing vendor quotes
Weak atSeeing total carpentry or total paintingExplaining to a client why the bedroom costs what it does
How to get bothSections = rooms, plus one "Whole Apartment" section for site-wide workCategory column = trade, totalled separately

Work that cannot honestly be split by room (painting the whole flat, floor protection, debris removal, deep cleaning) belongs in its own "Whole Apartment" section rather than being spread across rooms or buried in a single room's total. Here is the trade view of the worked example below: the same ₹6,70,000 of scope, regrouped by category.

Category (trade)Client amount (₹)Share of total
Carpentry & Woodwork4,95,70074.0%
Paint & Finishes88,40013.2%
Civil & Masonry (countertop)33,0004.9%
False Ceiling & POP21,6003.2%
Site Services & Cleaning20,5003.1%
Electrical & Lighting10,8001.6%
Total6,70,000100%

In the room view, carpentry is spread across four sections. In the trade view it is three quarters of the job. That is the number to have in mind when you negotiate with your carpentry contractor or decide where a rate review will matter most.

Units: one per item type, defined in writing

Units are where two BOQs for the same flat stop being comparable. Pick one unit for each type of item, write down how it is measured, and use it on every project. The table below reflects common practice in Indian residential interiors; what matters most is that your studio is consistent and that the description says how the quantity was measured.

ItemUnitHow it is measuredWatch for
Wardrobes, lofts, TV units, wall panellingsq.ftFinished face (elevation): width × heightState carcass and shutter material; say whether internal accessories are extra
Modular kitchen cabinetsrftRunning length of each bank, base and wall units on separate linesHardware and countertop are separate lines
Countertoprft or sq.ftRunning length at a stated depth, or areaSay whether sink and hob cut-outs and edge polish are included
False ceilingsq.ftCeiling area covered; bands and coves in rft if priced separatelySay whether lights and cut-outs are included
Paintingsq.ftWall and ceiling surface painted, not floor areaCoats, putty, primer and brand range belong in the description
Flooring and tilingsq.ftFinished floor area; skirting in rftState the wastage allowance and who supplies tiles
Electrical and plumbingnos (points)Count of pointsDefine a point: from where, which wire or pipe, whether the switch or fitting is included
Hardware and fittingsnos or setCountName the make, or write "as approved by client"
Site servicesLSOne line per service with its scope written outNever one "miscellaneous" line
Curtains and blindsrftTrack length; fabric separately if priced by the metreState fullness and lining

Lump sum is a unit, not a hiding place

LS (lump sum) is the right unit for work that is genuinely one job: floor protection for the duration of works, debris removal, deep cleaning before handover. It is the wrong unit for anything you could measure. A modular kitchen quoted as "1 LS" cannot be checked, cannot be compared, and cannot be adjusted fairly when the client drops the loft units. Each LS line should carry a description that says exactly what it covers.

Take quantities from the survey, not from memory

Quantities should trace back to a measurement: a wall length from the site survey, a cabinet run from the kitchen drawing. Writing the dimensions next to the quantity (8' × 7' beside 56 sq.ft) lets anyone in the studio check the arithmetic in a few seconds, and lets the site supervisor confirm the size before cutting starts.

Rates: internal cost, client rate and margin

Each line needs two rates. The internal rate is what the line really costs you: material at your vendor's price, labour, transport and any wastage you expect. The client rate is what you charge, before GST. The difference is the line's margin, and it is worth seeing line by line, because it rarely comes out even. In the worked example, the wardrobes earn 35.1% while the kitchen drawer hardware earns 25%.

One trap catches many studios: markup and margin are not the same number. Markup is added on top of cost. Margin is the share of the selling price you keep. A 30% markup on cost gives a 23.1% margin, not 30%.

Markup on costClient rate for ₹1,000 of costMargin on selling price
15%₹1,15013.0%
20%₹1,20016.7%
25%₹1,25020.0%
30%₹1,30023.1%
40%₹1,40028.6%
50%₹1,50033.3%

If your target is a 30% margin, the markup you need is about 43% (₹1,000 of cost sold at ₹1,429). Decide which of the two numbers your studio talks in, and write it on the costing sheet so nobody quotes on the wrong one.

Where contingency goes

Site surprises are normal: a wall out of plumb, an extra electrical run, a vendor price that moved. Rather than padding individual rates, keep a contingency as a percentage of your cost at the summary level. It is an internal number. The client sees your client rates; the contingency reduces the margin you expect to keep. There is no standard percentage. It depends on how well the site has been surveyed and how much of the scope is still undecided. The example below uses 5% purely to show the arithmetic.

GST: once, at the right rate

Keep client rates exclusive of GST and add GST at the summary, or per line when lines carry different rates. When a studio supplies material and labour together for fit-out work, the job is generally treated as a works contract. Secondary tax guides report that works contracts have attracted a flat 18% GST since 22 September 2025, under SAC heading 9954 (TaxClue, updated 18 August 2026). A design-only fee is a separate service. Because the classification depends on your contract and the client, confirm the rate and SAC code with your chartered accountant before you issue the quotation.

A worked example: 2 BHK BOQ

Here is the complete client-facing BOQ for an illustrative 2 BHK: living and dining, a modular kitchen, two bedrooms, and site-wide work. The rates are illustrative. They show the structure and the arithmetic, not market rates for your city. Every amount is quantity × client rate, and the total is the sum of the lines.

SectionItem and specificationUnitQtyClient rate (₹)Amount (₹)
Living & DiningFalse ceiling, gypsum board on GI framing, flat with covesq.ft18012021,600
Living & DiningTV unit, 18mm BWP ply, 1mm laminate, 7' × 4'sq.ft281,65046,200
Living & DiningElectrical points, new and shifted, with switch and platenos1290010,800
KitchenBase units, 18mm BWP carcass, acrylic shuttersrft1010,2001,02,000
KitchenWall units, 18mm BWP carcass, acrylic shuttersrft87,10056,800
KitchenTandem drawer set, soft-close, make as approvedset45,60022,400
KitchenQuartz countertop, 20mm, edge polish and sink cut-outrft103,30033,000
Master BedroomWardrobe, 18mm BWP carcass, 1mm laminate shutters, 8' × 7'sq.ft561,8501,03,600
Master BedroomWall panelling behind bed, 1mm laminate on 12mm ply, 10' × 9'sq.ft9075067,500
Bedroom 2Wardrobe, same specification, 6' × 7'sq.ft421,85077,700
Bedroom 2Study table with overhead shelf, 4' widenos119,50019,500
Whole ApartmentPainting: putty, primer and 2 coats emulsion, walls and ceilingssq.ft2,6003488,400
Whole ApartmentFloor and fixture protection for the duration of worksLS18,0008,000
Whole ApartmentDebris removal and deep cleaning before handoverLS112,50012,500
Whole ApartmentSofa and dining set: client supplied, excludednos100

The 15 lines total ₹6,70,000 before GST. Internally, the same BOQ carries an internal rate on each line. Rolled up by section, it shows where the margin sits:

SectionClient amount (₹)Internal cost (₹)Margin before contingency
Living & Dining78,60055,30029.6%
Kitchen2,14,2001,52,80028.7%
Master Bedroom1,71,1001,14,00033.4%
Bedroom 297,20064,40033.7%
Whole Apartment1,08,90077,40028.9%
Total6,70,0004,63,90030.8%

Then the summary adds contingency on cost and GST on the client total:

Summary lineAmount (₹)
Internal cost4,63,900
Contingency, 5% of internal cost23,195
Cost including contingency4,87,095
Client total before GST6,70,000
Estimated margin (client total minus cost including contingency)1,82,905 (27.3%)
GST at 18% on the client total1,20,600
Grand total to client7,90,600
Stacked bar showing how the 2 BHK example adds up: internal cost 4,63,900 rupees, contingency 23,195 rupees, estimated margin 1,82,905 rupees making a client total of 6,70,000 rupees before GST, then GST of 1,20,600 rupees for a grand total of 7,90,600 rupees
The client sees ₹6,70,000 plus GST. Your contingency comes out of the margin, not out of the client's pocket.

Three details in this example are worth copying. The client-supplied sofa and dining set appear as a zero line, so nobody assumes they were included. Painting, protection and cleaning sit in their own section instead of inflating one room. And the kitchen hardware is a separate line, so a client who asks for a cheaper make changes one line rather than the whole kitchen rate.

Exclusions, client-supplied items and open decisions

A BOQ is as much about what is not included as what is. Write these down explicitly:

  • Client-supplied items: loose furniture, appliances, light fittings the client is buying. List them at zero, as in the example, or in an exclusions note.

  • Items outside your scope: civil changes, society approvals, appliance installation, anything the builder still owes.

  • Open decisions: if the client has not chosen the countertop or the shutter finish, price your assumed option, name it in the description, and say that a different choice will be priced as a change.

  • Rate validity: how long the rates hold, since board, hardware and laminate prices move.

Once the client approves, treat the BOQ as the baseline. Later additions and removals become priced variations against it, not edits that quietly overwrite the approved version. The interior project management guide covers how that baseline then feeds drawings, procurement and client sign-off.

Before you send a BOQ

  • Every line has a specification: material, thickness, finish, make or "as approved"
  • Each item type uses your studio's standard unit, and the description says how it was measured
  • Electrical and plumbing points are defined
  • Every LS line says exactly what it covers; there is no "miscellaneous" line
  • Quantities trace back to the site survey or drawings, with dimensions shown
  • Hardware, countertops and appliances are separate lines
  • Internal rates are filled in for every line, so the margin is real
  • Client-supplied and excluded items are listed
  • GST rate and treatment confirmed; client rates shown before GST
  • Section subtotals and the grand total recalculated after the last edit
  • Rate validity and version number are on the document

Using the template in a spreadsheet or in DecorFlow

The template has one row per BOQ line and these columns: Section, Item Name, Category, Description, Dimensions, Unit, Quantity, Internal Rate, Client Rate and Procurement. The last three columns (Internal Amount, Client Amount and Margin %) are formulas, so they update when you change a quantity or rate. Replace the example rows with your own, keep the header row as it is, and save as CSV when you are done. Procurement says how a line will be bought (directMaterial, compositeTakeoff for assembled carpentry, serviceOnly, or excluded); you can leave it blank.

A spreadsheet works well for one project. It gets harder when the same rates are used across ten projects, the client asks for a third revision, and the purchase team needs the approved quantities. That is the point where studios move the BOQ into software.

In DecorFlow's BOQ, the structure in this article is built in: sections by room, a category per line, an internal rate and a client rate on each item, a Safety Buffer percentage for contingency, Apply Markup to set client rates from cost, and Tax Mode for GST (exclusive, inclusive, itemized or not shown). To bring in this template, create a BOQ, choose Import CSV and review the preview before confirming. A BOQ can also start from a completed site survey, from your catalogue, or from a saved template. When it is ready, Continue to Quotation builds the client quotation from the same lines, and approved quantities feed procurement.

BOQ is part of DecorFlow's paid plans and is included in the 30 days of Growth features every new account starts with, no credit card needed. After that, the account continues on the Free plan unless you choose a paid plan.

Common questions about interior BOQ format

Topics:#BOQ#interior BOQ format#cost estimation#quotations#GST#BOQ template